|
Problem Solved:
Modules and Connectors Cut Construction Costs
By Gil Ajero, Controls Engineer, TAS Energy
Rising
energy prices make efficiency a primary objective for many
industries, particularly power generation. One of the
fastest-growing power generation technologies is the high efficiency
gas turbine (GT).
In many utility systems, GTs are used to provide power on demand.
Unlike relatively larger coal-fired and nuclear base load generation
facilities, the power output from GTs can be ramped up and down very
quickly. This characteristic is especially important in modern
electrical power systems for two reasons.
First, utilities need peaking power that can be ramped up rapidly to
temporarily satisfy high demand, typically experienced on the
hottest summer days. Second, utilities need a power source that can
be quickly ramped up or down to compensate for the intermittent
nature of renewable power sources such as wind and solar.
To satisfy peak power demands, utilities worldwide are increasingly
turning to GTs, but these versatile power sources have an Achilles'
heel. The power output from a GT decreases as the outside ambient
air temperature and humidity increases, so peak power may not be
available when it’s most needed.
Fortunately, there’s a solution. As shown in the chart below, if the
inlet air of the gas turbine is cooled, the output power lost due to
high inlet air temperature can be recovered.

To
accomplish this air cooling, turbine inlet chilling (TIC) was
pioneered in the mid-1980s in commercial and industrial markets by
TAS Energy (TAS), and power producers now use the
technique worldwide to increase the output and efficiency of power
generating GTs.
Our turbine inlet chilling systems correct the derate effect caused
by high ambient temperature and humidity. By cooling the inlet
combustion air, GT output is increased by 12 to 30%, depending on
the GT model and the climate conditions.
Modules Make
Sense
As the
demand for power increases, current infrastructures are often
inadequately prepared to
meet energy needs, and site-built infrastructure solutions tend to
be costly and time-intensive. TAS had to make existing systems more
efficient, and build them in the shortest and most economical time
frame possible. Modular construction was the solution, provided via
packaged TIC systems built by TAS in the company’s Houston facility.
These TIC systems are provided for gas turbine, commercial HVAC, and
data center applications, and for organic Rankine cycle systems for
low-temperature industrial and geothermal power generation. All of
these systems are packaged in single or multiple modules designed to
reduce total costs, decrease total schedule, and leverage the
advantages of standardization available in a factory environment.
TAS TIC systems have a maximum size but multiple modules, and
therefore maximum capacity is limited only by shipping constraints.
Each module is a self-contained chiller plant, and when extra
capacity is needed, simply add more modules. This approach allows
the company to standardize TIC module construction, and provides
many benefits to customers.
Many industries are turning to modularization as an improvement to
traditional on-site construction, and power generation is no
exception. With modularization, components and subsystems are built
and tested off site, typically at the OEMs facility, then shipped to
the site. Once on site, these modules are interconnected with other
modules and with components and subsystems constructed on site.
Modularization has many advantages over on-site construction, as
summarized in
Table 1
below. Construction safety is a huge issue for
commercial industrial facilities, and a great way to reduce the
number of OSHA-recordable incidents is to cut on-site construction
hours. Not only do modules shift construction hours off site, they
also increase overall safety, because module construction can be
performed in a controlled shop floor environment.
Table 1: Advantages of Modules Over On-Site Construction
-
Reduces installation and start up time
-
Reduces on site construction hours and OSHA recordable incidents
-
Allows capacity to be added in defined increments
-
Saves space
-
Provides single source responsibility
Labor
efficiency is another reason for off-site module construction.
Operating facilities introduce a host of inefficiencies, including
security gate check in, compliance with union work rules, work
permit procurement, and coordination with plant operations and other
crafts. Off-site craftsmen can devote more hours to actual work, and
are often more efficient, because they work on the same types of
systems day in and day out.
When subsystems must be added to existing installations, modules are
often the best alternative, as total space requirements can be
reduced, and as downtime can be cut to an absolute minimum.
With modules, there is a definite alignment of interest between the
OEM and the client, as both parties favor comprehensive off-site
skid testing. It is much cheaper for a module builder to perform
shop testing and minimize on-site commissioning and start-up effort.
This dovetails with client desires to have delivered systems up and
running as soon as possible.
Because modules are completely tested before arriving on site, power
plant operators gain single source responsibility for any issues —
not always the case with the inherent complexities of on-site
construction.

When
fully tested modules arrive at a site, the main remaining task is
connection to on-site utilities and to other subsystems and
components. Reducing the time required to complete this task is a
primary goal of TAS, and it’s one of the main reasons why we make
extensive use of power and signal connectors.
Making Connection
On Site
Installing TIC systems on site can be a challenge, particularly as
many systems are retrofitted and must often be shoehorned into
existing facilities. Consequently, we’re constantly looking for ways
to simplify and expedite on-site installation, with modularization
of the TIC systems being the preferred solution.
TIC modules require three types of connections: process, power, and
signal. Process connections are primarily chilled water
piping from the module(s) to the GT and condensing water
piping to onsite-cooling towers.
A hardwired three-phase connection is required from the existing
plant utility system to provide primary operating power to the
modules. For projects with multiple modules — the bulk of our TIC
systems — the modules then need to be connected to each other for
primary three-phase power, secondary single-phase power, and control
signals.
On each TIC multi-module system, we designate one module as the
primary power source, and this master module’s Motor Control Center
(MCC) is hardwired to the plant’s power source. Primary three phase
operating power is then hardwired from this master module to each of
the other modules.
Secondary single-phase power for module utilities, such as air
conditioning and lighting, is also distributed from the MCC to each
module, and this secondary power distribution among the modules is
accomplished using
Phoenix Contact Pluscon
connector systems.
The master module also contains the programmable logic controller
(PLC) needed by each TIC system to provide control and monitoring.
Wiring to and from this PLC is distributed to other modules as
needed, also using the Pluscon connectors.
Before we started using connectors, the secondary power and control
connections among the containers were made using hard wiring. A
combination of wires and cables in flexible conduit was landed to
terminal blocks in a junction box installed between the modules.
These fully tagged wires and cables were disconnected from the
terminal block when the modules were split before shipment.
At the site, it took about three days for the module connections to
be re-terminated, with a couple of days more to clear out any
improper connections before final commissioning could take place.
This on-site activity is undertaken by an outside contractor, so
time and cost are issues.
Using connectors considerably reduced the time it took to reconnect
the modules, down to about a day or less,
from five days or more using hard wiring. In addition, the
connectors greatly reduced the incidence of incorrect wire
terminations. Finally, on-site contractor costs were substantially
reduced
(Table 2).
Table 2: Advantages of Connectors Over Hardwiring
-
Transfers wiring labor from field to shop
-
Speeds installation
-
Cuts installation costs
-
Reduces installation wiring errors
-
Makes it easier to provide
spare capacity
Before
selecting the Phoenix Contact connectors, TAS evaluated competing
solutions. At the time of selection, the company was already using
Phoenix Contact terminal blocks and was pleased with their
performance, so it was natural to consider the company as a
connector supplier. Taking into account the different types of
signal wiring as well as power needs, no other supplier offered
industrially rugged connectors that could meet the requirements.
There were some design challenges, including identifying the higher
ampacity connectors with the correct size hub to accommodate the
increased cable sizes. Also, initial designs used too many different
types of connectors, but revisions were able to standardize with
just three types: 6-pin, 12-pin, and 24-pin.

Finally,
the design also needed to ensure that all power sources would always
end with female rather than male
connectors, to
guarantee that connectors are still touch-safe in the event of an
accidental disconnect while power is live. If a power source ends
with a male connector and the same situation occurs, an
OSHA-reportable incident would likely occur due to the presence of
unprotected live connector pins.
Now that TAS has a standardized and implemented connector design,
the company is realizing multiple benefits in addition to the
aforementioned installation advantages. Once the connections are
tested at the shop, splitting the modules is clean and easy, and
on-site reconnection is quick and accurate. Connectors lend
themselves to spare capacity, so future additions have become much
easier to wire.
Phoenix Contact’s Pluscon connectors have proven to be robust, heavy
duty, and well suited to this application. Termination onto the
male/female pins requires extra hours at the shop, but the reduced
time needed in the field during installation and start up more than
compensates.
TAS is seeing new customer demand that will require us to develop
non-standard products, both smaller and larger in overall total
system footprint. For larger capacity projects, that translates to
more modules and more split points, further driving the need for
expanded use of connectors.
TIC systems help our customers run more efficiently. Delivering
these systems as modules provides a host of benefits to our
customers, and also helps our company control the construction
process more closely while reducing costs. Using connectors to link
these modules at our customers’ sites provide further benefits to
our company, and most importantly to our customers.
Gil
Ajero is the controls engineer at
TAS Energy. Ajero can be reached at
gajero@tas.com. |
|